Cal-Sag Crossing 

Cal Sag.jpg

Project ID: AWSP-07-01

 

Project Description: Approximately 600 feet of 66" diameter transmission main in rock tunnel

Project Area: Palos Hills, Palos Park

Project Status: Design

 

Bid Advertisement Date:  October 2026

 

Construction Start Date: Q2 2027

Construction Completion Date: Q2 2029

 

Contractor Name: TBD

Submit construction questions or comments to construction@gpwc-il.org 

or by calling 833.815.GPWC (833.815.4792)

Project Notes

Updated 6/11/26 The design team has submitted the 90% design documents for review.

Updated 5/01/26 The design team is nearing completion of the 90% design documents.

Updated 12/17/25 The design team has completed the 60% design review process and is moving into 90% design. 

Updated 10/6/25 The design team has submitted the 60% design documents for review.

Updated 9/5/25 Design in progress. Field investigations complete.

Updated 7/4/25  Design in progress. Field investigations ongoing.  

Updated 4/4/25  Design in progress; Access permit for field investigations approved