Water Delivery Structures 3

Project ID: AWSP-06-08
Project Description: Construction of three water delivery structures; Instrumentation and controls for 7 structures
Project Area: Joliet, Channahon, Minooka, Shorewood, Crest Hill
Project Status: Bidding
Bid Advertisement Date: 09/10/2026
Construction Start Date: Q1 2027
Construction Completion Date: Q4 2028
Contractor Name: TBD
Submit construction questions or comments to construction@gpwc-il.org
or by calling 833.815.GPWC (833.815.4792)
Project Notes
Updated 09/17/2026 Bids for construction are due on October 29, 2026.
Updated 08/20/2026 The design team has submitted the 100% design documents for review.
Updated 06/11/2026 The design team has completed the 90% design review process and is moving into 100% design.
Updated 05/01/2026 The design team has submitted the 90% design documents for review.
Updated 04/13/2026 The design team is nearing completion of the 90% design documents.
Updated 12/17/2025 The design team has completed the 30% design review process and is moving into 90% design.
Updated 10/06/2025 The design team has submitted the 30% design documents for review.
Updated 09/05/2025 The design team is nearing completion of the 30% design documents.
Updated 04/04/2025 Design in progress.