Water Delivery Structures 1

Project ID: AWSP-06-06
Project Description: Construction of four water delivery structures
Project Area: Joliet, Channahon, Minooka
Project Status: Construction
Bid Advertisement Date: 09/04/2025
Construction Start Date: June 2026
Construction Completion Date: Q4 2026
Contractor Name: PirTano Construction Company, LLC
Submit construction questions or comments to construction@gpwc-il.org
or by calling 833.815.GPWC (833.815.4792)
Project Notes
Updated 10/23/2026 The work at the structures in Channahon and Minooka is nearing completion with the driveways and smaller items remaining. Work at the Joliet location is underway and the concrete is being installed.
Updated 09/17/2026 The contractor continues with work at 3 locations, 2 in Minooka and 1 in Channahon. Work at the Joliet location is expected to begin in October.
Updated 08/20/2026 Contractor continues with work at 3 locations (2 in Minooka and 1 in Channahon).
Updated 07/15/2026 Contractor is currently excavating and installing concrete at 3 of the 4 locations
(2 in Minooka and 1 in Channahon).
Updated 06/11/2026 Construction fencing has been installed at all locations. Excavation has begun at the Minooka Primary and Channahon Primary locations.
Updated 05/01/2026 The contractor is tentatively planning to begin construction at the Minooka location in mid-May.
Updated 02/27/2026 Contractor has begun schedule development and coordination. Construction activity expected to begin in April of 2026.
Updated 02/11/2026 Construction Notice to Proceed issued on 01/20/2026.
Updated 11/14/2025 Evaluation of the bids for construction is ongoing.
Updated 10/06/2025 Bids for construction are due on October 24, 2025.
Updated 07/04/2025 Design nearly complete; documents being prepared for bidding in the Fall. IEPA construction permit received.
Updated 06/10/2025 Design nearly complete. Documents being prepared for bidding in the Fall.
Updated 04/04/2025 Design in progress.
