Water Delivery Structures 1

Project ID: AWSP-06-06
Project Description: Construction of four water delivery structures
Project Area: Joliet, Channahon, Minooka
Project Status: Construction
Bid Advertisement Date: 09/04/2025
Construction Start Date: June 2026
Construction Completion Date: Q4 2026
Contractor Name: PirTano Construction Company, LLC
Submit construction questions or comments to construction@gpwc-il.org
or by calling 833.815.GPWC (833.815.4792)
Project Notes
Updated 09/17/2026 The contractor continues with work at 3 locations, 2 in Minooka and 1 in Channahon. Work at the Joliet location is expected to begin in October.
Updated 08/20/2026 Contractor continues with work at 3 locations (2 in Minooka and 1 in Channahon).
Updated 07/15/2026 Contractor is currently excavating and installing concrete at 3 of the 4 locations
(2 in Minooka and 1 in Channahon).
Updated 06/11/2026 Construction fencing has been installed at all locations. Excavation has begun at the Minooka Primary and Channahon Primary locations.
Updated 05/01/2026 The contractor is tentatively planning to begin construction at the Minooka location in mid-May.
Updated 02/27/2026 Contractor has begun schedule development and coordination. Construction activity expected to begin in April of 2026.
Updated 02/11/2026 Construction Notice to Proceed issued on 01/20/2026.
Updated 11/14/2025 Evaluation of the bids for construction is ongoing.
Updated 10/06/2025 Bids for construction are due on October 24, 2025.
Updated 07/04/2025 Design nearly complete; documents being prepared for bidding in the Fall. IEPA construction permit received.
Updated 06/10/2025 Design nearly complete. Documents being prepared for bidding in the Fall.
Updated 04/04/2025 Design in progress.
