top of page

Finished Water Transmission Main
(Segment F)

02-06.jpg

Project ID: AWSP-02-06

​

Project Description:  5.5 miles of 60" diameter water transmission main

​

Project Area: Crest Hill, Joliet

​

Project Status: Design

 

Bid Advertisement Date: November 2026

 

Construction Start Date: Q2 2027

 

Construction Completion Date: Q4 2028

 

Contractor Name: TBD

Submit construction questions or comments to construction@gpwc-il.org 

or by calling 833.815.GPWC (833.815.4792)

Project Notes

Updated 08/20/2026  The design team has completed the 90% design review process and is moving into 100% design.

Updated 06/11/2026  The design team has submitted the 90% design documents for review.

Updated 05/20/2026  The design team is nearing completion of the 90% design documents.

Updated 03/17/2026  Field investigations complete.

Updated 12/17/2025  The design team is nearing completion of the 90% design documents.

Updated 09/05/2025  Design is ongoing. Supplemental field investigations ongoing.

Updated 08/01/2025  The design team is nearing completion of the 90% design documents.

Updated 04/04/2025  Design in progress. Field investigations complete.