Finished Water Transmission Main
(Segment D)

Project ID: AWSP-02-04
Project Description: 7 miles of 66" diameter water transmission main
Project Area: Lemont, Palos Park, Romeoville
​
Project Status: Design
Bid Advertisement Date: Q3 2026
Construction Start Date: Q4 2026
Construction Completion Date: Q3 2029
Contractor Name: TBD
Project Notes
Updated 2/21/25 Design in progress