Finished Water Transmission Main
(Segment D)

02-04.jpg

Project ID: AWSP-02-04

 

Project Description: 7 miles of 66" diameter water transmission main

 

Project Area: Lemont, Palos Park, Romeoville

​

Project Status: Design

 

Bid Advertisement Date: January 2027

 

Construction Start Date: Q3 2027

 

Construction Completion Date: Q1 2030

 

Contractor Name: TBD

Submit construction questions or comments to construction@gpwc-il.org 

or by calling 833.815.GPWC (833.815.4792)

Project Notes

Updated 08/20/2026  The design team has submitted the 90% design documents for review.

Updated 07/15/2026  Supplemental field investigations planned.

Updated 06/11/2026  The design team is nearing completion of the 90% design documents.

Updated 03/17/2026  Field investigations complete.

Updated 12/17/2025  90% design work is ongoing.

Updated 11/14/2025  Supplemental field investigations ongoing.

Updated 10/06/2025  The design team has completed the 60% design review process and is moving into 90% design. 

Updated 09/05/2025  The design team has submitted the 60% design documents for review.

Updated 04/04/2025  Design in progress. Field investigations ongoing.