top of page
Finished Water Transmission Main
(Segment B)

Project ID: AWSP-02-02
Project Description: 5 miles of 66" diameter water transmission main
Project Area: Bridgeview, Hickory Hills, Palos Hills
​
Project Status: Design
Bid Advertisement Date: Q4 2026
Construction Start Date: Q2 2027
Construction Completion Date: Q3 2029
Contractor Name: TBD
Project Notes
Updated 2/21/25 Design in progress
bottom of page